We congratulate our engineer @Daniele Koetting who WON the “MODEST MODEL COMPETITION” AWARD with the project of the “New Production Plant on behalf of OSAI Automation System SPA @osai, to be built in the municipality of Samone (TO)”.
The factory will be built with a prefabricated reinforced concrete structure, with the exception of the stairwells, elevator shafts and foundations. The foundation system is characterized by plinths on piles connected by a slab and foundation beams. The floors of the building will be made using TT tiles. Given the considerable surface extension of the construction, a structural joint will be created.
Method and calculation code: Master-Slave method and structural analysis of the Linear Dynamic Seismic Analysis type
Non-dissipative structural behavior with a behavior factor q equal to 1.50, as foreseen in par. 7.3.1 of the 2018 NTCs.
Base model: Rhinoceros (no BIM software)
Plug-in for BIM interoperability: VisualARQ
BIM software: ModeSt to perform the structural analysis of the building
Structural element sizing: ModeSt ver. 8.26, produced by Tecnisoft Harpaceas, implementing a linear dynamic seismic analysis.
Client: Osai Automation System
Dimension: 3,800 m2
Architectural design: Sertec
Structural Project: Sertec
MEP Project: Sertec
We thank @Harpaceas Srl for organizing the competition and for giving us the opportunity to publish our project as a Case History